Road Work Ahead: KDOT 2014 Resurfacing Projects Start May 5
County Highway and order of construction |
From |
To |
Healy Road |
Bliss Road |
Tanner Road |
Meredith Road |
1,000 feet north of IL Route 38 |
McNulty Road |
McGough Road |
Peplow Road |
IL Route 64 |
French Road |
IL Route 72 |
Main St (Burlington Road) |
Allen Road |
Harmony Road |
Brier Hill Road |
Getty Road |
Harmony Road |
IL Route 20 |
Big Timber Road |
IL Route 72 |
Randall Road |
Rippburger Rd / Russell Rd |
Plato Rd |
Plank Road |
Plato Road |
IL Route 47 |
Muirhead Road |
Corron Road |
Bowes Road |
McDonald Road |
Silver Glen Road |
Corron Road |
Randall Road |
Randall Road |
Ferson Creek bridge |
Red Haw Lane |
Keslinger Road |
Brundige Road |
Randall Road |
Fabyan Parkway |
Kirk Road |
Kane / DuPage Co Line |
Resurfacing will start with Healy Road milling on May 5, 2014 and will continue in the order as listed above. The resurfacing process typically includes:
- Grinding & removal of 1 1⁄2” to 3” of the top wearing surfacing of pavement
- Placement of a fresh oil application over the grinded pavement
- Placement of 2 1⁄4” to 3.0” of an asphalt layer over the oil application to provide a new smooth riding surfaceTemporary daily lane closures from 6:00 am to 6:00 pm Monday through Saturday will be required to accomplish this work. Please watch out for fresh oil signs and flaggers, and reduce speed while traveling through the construction zone. Motorist should expect delays, increased travel times during the resurfacing process and are advised to consider alternate routes during this work.Questions or concerns may be directed to John Guddendorf at (630) 816-9671. For all Kane County Traffic Advisories, see http://www.co.kane.il.us/dot/trafficalerts/Default.aspx.